Microsoft Managing Programs and Projects with Project Server 2013 - 074-344 Exam Practice Test
You are a project manager for an organization that uses Project Server 2013.
You have many projects that you schedule and manage. Your organization hires an individual that will be a resource on one of your schedules.
You need to use Project Web App (PWA) to add the resource to your schedule as a Team Member so that you can assign them tasks.
What should you do?
You have many projects that you schedule and manage. Your organization hires an individual that will be a resource on one of your schedules.
You need to use Project Web App (PWA) to add the resource to your schedule as a Team Member so that you can assign them tasks.
What should you do?
Correct Answer: A
You are a team member for an organization that assigns your tasks on schedules. Single-entry mode is not enabled.
At the end of the week, you submit your timesheet in Project Server 2013. Default security settings are enabled. However, a task assigned to you should have been assigned to a coworker who does the same type of work and who has other tasks on the schedule.
The project manager who assigns the tasks is unavailable.
You need re-assign this task to your co-worker.
What should you do?
At the end of the week, you submit your timesheet in Project Server 2013. Default security settings are enabled. However, a task assigned to you should have been assigned to a coworker who does the same type of work and who has other tasks on the schedule.
The project manager who assigns the tasks is unavailable.
You need re-assign this task to your co-worker.
What should you do?
Correct Answer: D
You are a portfolio manager for an organization that uses Project Server 2013.
You plan to create weekly status project reports for your executive team. You want to publish your report only once in Project Web App (PWA). Users must be able to fully interact with the report by adding or excluding fields and by changing the rows or columns fields.
You need to create a report that meets these requirements.
What should you do?
You plan to create weekly status project reports for your executive team. You want to publish your report only once in Project Web App (PWA). Users must be able to fully interact with the report by adding or excluding fields and by changing the rows or columns fields.
You need to create a report that meets these requirements.
What should you do?
Correct Answer: C
You are a program manager in an organization that uses Project Server 2013. The allow master projects to be saved and published function is not enabled.
Your program contains seven active projects managed in Project Online.
You need a way to review the tasks flagged as milestones in all seven active projects at one time.
You open Project Center in Project Web App (PWA).
What should you do next?
Your program contains seven active projects managed in Project Online.
You need a way to review the tasks flagged as milestones in all seven active projects at one time.
You open Project Center in Project Web App (PWA).
What should you do next?
Correct Answer: B
You are a project manager who uses Project Server 2013 and Project Professional 2013.
You are managing a project that has already begun. A new change request has been pre-approved, and the director wants to understand the impact to the overall project schedule prior to formally approving the project to include in the project schedule.
You add the change request to your project schedule. Your original baseline is Baseline1.
You need to include the change request in your baseline to see the impact of your overall project schedule including duration, work, and cost.
What should you do?
You are managing a project that has already begun. A new change request has been pre-approved, and the director wants to understand the impact to the overall project schedule prior to formally approving the project to include in the project schedule.
You add the change request to your project schedule. Your original baseline is Baseline1.
You need to include the change request in your baseline to see the impact of your overall project schedule including duration, work, and cost.
What should you do?
Correct Answer: A
You are in the Project Management Office (PMO) for a company that uses Project Online to select portfolios for each business unit.
The parameters used as cost constraints vary from department to department, including Cost, CapEx, and Estimated Hours. You are responsible for providing the infrastructure to support the various constraints.
You need to select a feasible method for employing cost constraints.
Which two fields should you use? (Each correct answer presents part of the solution. Choose two.)
The parameters used as cost constraints vary from department to department, including Cost, CapEx, and Estimated Hours. You are responsible for providing the infrastructure to support the various constraints.
You need to select a feasible method for employing cost constraints.
Which two fields should you use? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: C,D
You work in the Project Management Office (PMO) for an organization that uses Project Server 2013. Team members enter task updates in Project Web App (PWA), and project managers review these updates in PWA.
You discover that team members enter hours worked each day on your project, but they enter percent complete on another project.
You need to limit the task update method across the enterprise to one method for team members.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You discover that team members enter hours worked each day on your project, but they enter percent complete on another project.
You need to limit the task update method across the enterprise to one method for team members.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: A,D
You are a project manager who uses Project Server 2013.
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?
Correct Answer: D
You work for an organization that uses Project Server 2013.
You are updating your assigned task information from your Microsoft SharePoint task list.
You need to ensure that the appropriate fields are updated.
Which three standard fields can be updated when in SharePoint? (Each correct answer presents a complete solution. Choose three.)
You are updating your assigned task information from your Microsoft SharePoint task list.
You need to ensure that the appropriate fields are updated.
Which three standard fields can be updated when in SharePoint? (Each correct answer presents a complete solution. Choose three.)
Correct Answer: A,B,E
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?
Correct Answer: B