Oracle Primavera P6 2021 Enterprise Project Portfolio Management - 1Z0-129 Exam Practice Test

You are developing a reporting strategy for a customer who requires monthly reports showing cost variance. The customer has two requirements.
1. Each report must come from Primaver
a.
2. Each month''s report must become a "snapshot" for legal traceability purposes. Which P6 R8 solution addresses each of the customer''s requirements?
Correct Answer: A
Non-assignees users who can edit a specific step in a Business Process when it is in draft mode are called.
Correct Answer: B
Identify two statements that best describe how Role Teams are used.
Correct Answer: D,E
When can an assignee decline a task if an option is enabled for a step?
Correct Answer: C
Identify the administration level that manages licenses.
Correct Answer: C
In addition to the four primary elements that comprise security, what additional feature in P6 Web will determine a user's access to data?
Correct Answer: A
You are manually adding users to Unifier. You notice that your newly added users are inactive. What is the reason for this?
Correct Answer: D
You are a Program Manager reviewing Portfolio Performance dat
a. You see a number of Issues that are assigned to a Responsible Manager. What does Responsible Manager mean within Primavera P6 EPPM?
Correct Answer: B
View the Exhibit.

Which two statements about the date formula built on the Vendor Active Date field are true?
Correct Answer: E
What is a resolving Condition?
Correct Answer: A
What determines the availability of Details Forms and Line Item lists when creating a Business Process?
Correct Answer: A
Select the true statement regarding the ability to create projects.
Correct Answer: B
You are a Portfolio Manager with a filter that has been set to identify and assign projects to your portfolio. You are in Primavera P6 EPPM Web Interface. How could you be certain that the list of projects in your portfolio is complete?
Correct Answer: C