IBM Assessment: IBM WebSphere Lombardi Edition V7.2, BPM Program Management - A2180-188 Exam Practice Test
Within a business process application, access to business data in other systems is accomplished via:
Correct Answer: D
After a successful Playback 0, stakeholders excitably request that Playback 1 should be a fully functional application with look and feel branding and several features used in other core company applications. How should the program manager respond?
Correct Answer: C
Process business data that needs to be available after the process instance completes must be:
Correct Answer: B
A program manager is helping an organization optimize their BPM development practices. After talking with the development leads of a number of projects, the program manager suspects that there is a lot of duplication of effort between the projects. What is the first thing the program manager should recommend to reduce this duplication of efforts?
Correct Answer: D