SAP Certified Associate - SAP S/4HANA Asset Management - C-P2W43-2023 Exam Practice Test
Which are the prerequisites for Inspection Checklist Processing? Note: There are 2 correct answers to this question
Correct Answer: A,D
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
Correct Answer: B
Which of the following parameters are available when you define a new maintenance plan category? Note: There are 3 correct answers to this question.
Correct Answer: A,B,C
Which operations can the responsible person perform after a maintenance order is technically completed? Note: There are 2 correct answers to this question
Correct Answer: A,D
How does a maintenance request within the phase-based process differ from a maintenance notification in the standard process?
Correct Answer: D
Which operations are possible when you cancel the technical completion of a maintenance order? Note: There are 2 correct answers to this question
Correct Answer: C,D
Where can the maintenance planner perform a material availability check? Note: There are 2 correct answers to this question?
Correct Answer: A,B
What do you have to consider regarding a cross-plant planning scenario?
Correct Answer: A
The maintenance technician wants to document work steps for a technical object in a notification. What are the best options to be used in regard to code-based reporting? Note: There are 2 correct answers to this question?
Correct Answer: A,D