You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
Correct Answer: B
Where do you maintain the duration of a product on operation?
Correct Answer: D
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note: There are 2 correct answers to this question.
Correct Answer: B,D
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.
Correct Answer: B,C
What is the purpose of collective orders?
Correct Answer: D
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
Correct Answer: B
During production order creation, several valid production versions are found. How does the system choose the product conversion?
Correct Answer: D
You want to schedule an order in the graphical planning board. What are valid planning directions?
There are 2 correct answers to this question.
There are 2 correct answers to this question.
Correct Answer: A,C