SAP Certified Application Associate - Planning and GATP in SAP SCM APO 7.0 EHP1 - C-TSCM44-65 Exam Practice Test

You have to define selections in SNP.
Apart from the SNP Planner, which fields can you use?
Correct Answer: D
How does the system handle data with consistent planning in DP?
Note: There are 3 correct answers to this question.
Correct Answer: B,C,E
An employee uses the detailed scheduling planning board in APO-PP/DS. Although a particular resource is visible on the board, the employee is unable to plan any operations on it.
What is the reason for this?
Correct Answer: A
Which of the following steps are necessary to generate an RFC connection that can be used for the APO Core Interface?
Note: There are 3 correct answers to this question.
Correct Answer: B,C,D
Interchangeability master data is maintained in transaction /INCMD/UI.
What do you have to do in order to use the product and/or location interchangeability master data in GATP?
Note: There are 2 correct answers to this question.
Correct Answer: A,D
Your customer is using the ECC planning transaction for repetitive manufacturing as shown in the screenshot.
Which planning transaction in SCM do you have to configure to offer the same "look and feel"?
Correct Answer: A
The customer needs a FORECAST key figure that is disaggregated initially according to historical data. With planned data, the FORECAST has to be calculated according to the ratio of the detailed planned data.
In which of the following cases is this possible?
Correct Answer: B
You want to define virtual safety stock within PP/DS.
Which statements correctly describe this kind of modeling?
Note: There are 3 correct answers to this question.
Correct Answer: A,B,C