SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 - C_TPLM22_67 Exam Practice Test
What are the three areas of the project screen?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
Which indicator automates the grouping of project stock assigned to individual WBS elements to the top WBS element?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Which of the following combination of assignment to an externally-processed activity allows you to carry out capacity planning for your vendors?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Which of the following statements concerning ProMan are correct? (5)
Correct Answer: A,B,D,E,F
Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Could a user with Access Control List (ACL) authorization 'Read' lock a project?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,E
How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
How are cost-relevant items determined for stock materials while using planned costs in networks?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
When you create service activity in your network, what data can be entered? (3)
Correct Answer: B,C,D