SAP Certified Application Associate - SAP S/4HANA Project Systems - C_TS412_1909 Exam Practice Test
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However,
the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
Correct Answer: A,B
Your customer has created networks with internal activities and generated capacity requirements. Now,
they want to analyze the capacity requirements of their project. Which report do you recommend?
they want to analyze the capacity requirements of their project. Which report do you recommend?
Correct Answer: A
Material
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events.
What is the requisites for implement scheduling of events?
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events.
What is the requisites for implement scheduling of events?
Correct Answer: C
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
Correct Answer: A,B
Resources
You Want assign milestone to WBS element? For what can you use these milestone.
You Want assign milestone to WBS element? For what can you use these milestone.
Correct Answer: B
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
Correct Answer: C,E
Project Structure
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times.
Therefore they want to get an overviews of the budget updates.
What standard report do you recommend?
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times.
Therefore they want to get an overviews of the budget updates.
What standard report do you recommend?
Correct Answer: B
How are earliest dates and latest dates of activities scheduled?
Correct Answer: B
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
Correct Answer: B,C,E