SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 - C_TSCM42_66 Exam Practice Test
Which of the following are characteristics of ECC master production scheduling (MPS)?(Choose three)
Correct Answer: B,D,E
Where can you define the default storage location for the material component of a production order?(Choose three)
Correct Answer: A,B,D
What do you have to consider when you use SAP ECC long-term planning (LTP)?(Choose two)
Correct Answer: B,D
The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order.
However, a corresponding rescheduling exception message does not appear.
What could be the reasons?(Choose two)
However, a corresponding rescheduling exception message does not appear.
What could be the reasons?(Choose two)
Correct Answer: B,C
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
Correct Answer: C
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).
Which of the following properties for the resulting dependent requirements applies?
Which of the following properties for the resulting dependent requirements applies?
Correct Answer: D
What is a feature of the simu-lation mode for material requirements planning in SAP ECC?
Correct Answer: B
Which functions can be triggered before releasing a production order?(Choose three)
Correct Answer: A,B,E