CompTIA Project+ - PK0-400 Exam Practice Test
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?
Which of the following are critical for the project manager to provide?
Correct Answer: D
Which of the following describes a burn rate?
Correct Answer: B
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Correct Answer: A
A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.
The project manager is concerned that the requests will lead to:
The project manager is concerned that the requests will lead to:
Correct Answer: B
A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?
Which of the following is the BEST way for the project manager to address the issue?
Correct Answer: C
The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
Correct Answer: B
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
Correct Answer: A
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
Correct Answer: C
Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
Correct Answer: B
Which of the following are examples of organizational change? (Choose two.)
Correct Answer: A,C