PMI Risk Management Professional - PMI-RMP Exam Practice Test

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime.
However, this action may lead to excessive additional cost.
What should the risk manager do?
Correct Answer: B
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
A project manager was informed that the testing of the latest component in the project ' s software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.
What should the risk manager do next to understand the differences between planning and execution?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
A project manager has requested the risk manager ' s support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.
What should the risk manager recommend?
Correct Answer: D
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
What will help calculate the impact?
Correct Answer: D
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.
What should the project manager do next?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.
Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
Correct Answer: B
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.
What should the risk manager do with this risk?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.
What should the risk manager do?
Correct Answer: B
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).