You are the project manager for your organization. You are working with your virtual team to create activity duration estimates for your current project. This virtual team is comprised of team members from around the world. Much of this process will be completed by geographical locations though some conferences will require all the team members to participate and to coordinate the activities that will interact between the different sites. The project manager must consider all of the following when creating the activity duration estimates except for which one?
Correct Answer: D
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?
Correct Answer: B
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?
Correct Answer: B
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
What is the formula to find the schedule performance index?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule. Which of the following is a tool and technique for the Schedule Development process?
Correct Answer: B
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?
Correct Answer: A
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about fast tracking the project?
Correct Answer: A
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work. Which of the following is the input to monitor and control project work?
Correct Answer: A
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
You work as a project manager for BlueWell Inc. Which of the following tools/techniques will you use to demonstrate how a process behaves over time, and when a process is subject to special cause variation, resulting in an out-of-control condition?
Correct Answer: D
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?
Correct Answer: B
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?
Correct Answer: C
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).