PMI Program Management Professional (PgMP) - PgMP Exam Practice Test

You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?
Correct Answer: C
A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha's program closure plan?
Correct Answer: D
A complex technology program consisting of nine projects is at risk of delayed deliverables. A team member found a valid alternative solution that allows parallel implementation of three components previously planned to be implemented sequentially. Which document should the program manager update?
Correct Answer: A
Explanation: Only visible for TrainingDump members. You can sign-up / login (it's free).
Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work.
Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?
Correct Answer: D
The consulting company has created the scope of work for the project. They are in the process of creating a schedule and budget. They have added time into the schedule for the delays that always happen. They are also allocating money into the budget for more computers and software that are usually needed beyond what is initially forecast. These items are an example of what?
Correct Answer: A
Which of the following best relates to unknown unknowns?
Correct Answer: D
A program manager is developing a program management plan by integrating the plans of constituent projects. During this effort, the program manager learns that a resource is critical to more than one component and there is a time overlap for their availability. When creating the program resource management plan, what should the program manager do first?
Correct Answer: D
During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
Correct Answer: D
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
Correct Answer: B
Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?
Correct Answer: A
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement.
What should the program manager do first?
Correct Answer: B