BICSI Registered Communications Distribution Designer (RCDD) - RCDDv14 Exam Practice Test

Which two of the following may the ICT distribution designer need to provide in order to identify the BEST solutions for the client's need? (Select two options.)
Correct Answer: A,E
In a design type Scope of Work (SoW) the ICT distribution designer is responsible for providing
Correct Answer: C
Which of the following is TRUE about convenience receptacles?
Correct Answer: B
A project's closeout plan will be executed by the project manager (PM) and will be managed and approved by the
Correct Answer: A
Identify the core switch(es) and server(s) of the data center in the diagram below by dragging the appropriate term into each box in the diagram.
Correct Answer:

In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.
Correct Answer: C
You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%. What size commercial DD (distribution device) is required to accommodate the increase?
Correct Answer: A
In new construction, what is the percentage of pay phones that must be equipped with volume controls?
Correct Answer: B
A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).
What should the program manager update?
Correct Answer: A
Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?
Correct Answer: C
A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
Correct Answer: C
The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization What should the program manager do next?
Correct Answer: A
An ICT distribution designer is representing a client during a project execution. What is the designer's role in the Vendor and Contractor Coordination?
Correct Answer: D