NEW QUESTION 45
Which of these are layers in SAP Best Practice content?
There are 3 correct answers to this question.
Response:
- A. Solution packages
- B. Configuration guides
- C. Process diagrams
- D. Building blocks
- E. Scope items
Answer: A,D,E
NEW QUESTION 46
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Control cycle
- B. Rate routing
- C. Production supply area
- D. Replenishment strategy
Answer: A
NEW QUESTION 47
Which of the following data objects are updated when a user confirms an operation?
Please choose the correct answer.
Response:
- A. Shop floor information system
- B. Production order header status
- C. Warehouse transfer order status
- D. Production order total order quantity
Answer: A
NEW QUESTION 48
What determines whether the planned independent requirements in MRP consume other requirements?
- A. Order type
- B. Requirements profile
- C. Consumption sequence procedure
- D. Requirements type
Answer: D
NEW QUESTION 49
How can Production Planning and Detailed Scheduling (PP/DS) enhance the standard planning functionality?
Please choose the correct answer.
Response:
- A. By providing future demands from demand figures in the past
- B. By providing cross-plant planning and deployment
- C. By providing replenishment proposals with exact times
- D. By providing multilevel material requirements planning
Answer: C
NEW QUESTION 50
In Make-to-order production, which field controls whether the components will be planned as sales order specific stock?
Please choose the correct answer.
Response:
- A. The item category of the component in the BOM
- B. The Planning Strategy of the finished product
- C. The Individual/Collective indicator of the component
- D. The MRP Type of the component
Answer: B
NEW QUESTION 51
Which process order function uses a resource network?
Please choose the correct answer.
Response:
- A. Capacity planning
- B. Capacity leveling
- C. Resource selection
- D. Resource scheduling
Answer: C
NEW QUESTION 52
How would you define pegging in the context of Advanced Planning?
- A. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
- B. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
- C. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
- D. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
Answer: B
NEW QUESTION 53
Which of the following objects can you release so that the business transactions for process order execution and process management can be executed?
There are 2 correct answers to this question.
Response:
- A. Individual control recipes
- B. Individual process instructions
- C. Individual operations
- D. Individual phases
Answer: C,D
NEW QUESTION 54
How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers to this question.
- A. Predefined GMP compliant process order types to meet audit requirements
- B. Documentation of quality data with Quality Management
- C. Recipe approval (with Engineering Change Management)
- D. Use of the GMP compliant flag in relevant master data applications
- E. Use of the digital signature function to check and run business processes
Answer: B,C,E
NEW QUESTION 55
What does a line hierarchy in repetitive manufacturing represent?
- A. A production line with a parallel sequence in the routing
- B. A production line with prioritized alternative work centers
- C. A production line with an alternative sequence in the routing
- D. A production line with more than one work center
Answer: D
NEW QUESTION 56
Which Kanban master data object controls the relationship between the supply and demand source?
Please choose the correct answer.
Response:
- A. Kanban container
- B. Control cycle
- C. Rate routing
- D. Production supply area
Answer: B
NEW QUESTION 57
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
- A. Insert operation
- B. Scheduling working time only
- C. Find Slot
- D. Squeezing
Answer: C
NEW QUESTION 58
Which task list types can have parallel sequences?
There are 2 correct answers to this question.
Response:
- A. Rate routings (R)
- B. Reference operation sets (S)
- C. Master recipes (2)
- D. Routings (N)
Answer: A,D
NEW QUESTION 59
You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: There are 2 correct answers to this question.
- A. Checking rule and group must be assigned.
- B. PRT Availability check must be set.
- C. Indicator Relevant for finite scheduling must be set.
- D. Checking control must have an overall profile assigned in customizing.
Answer: C,D
NEW QUESTION 60
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a negative planning horizon in the strategy profile.
- B. Specify a positive planning horizon in the strategy profile.
- C. Specify a positive offset time in the strategy profile.
- D. Specify a negative offset time in the strategy profile.
Answer: D
NEW QUESTION 61
......
SAP C_TS422_1909 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
| Topic 7 |
|
| Topic 8 |
|
| Topic 9 |
|
C_TS422_1909 Exam Certification Details:
| Exam: | 80 questions |
| Cut Score: | 55% |
| Duration: | 180 mins |
100% Free C_TS422_1909 Daily Practice Exam With 91 Questions: https://www.trainingdump.com/SAP/C_TS422_1909-practice-exam-dumps.html